Show Hammock allocation in a column at task level?

4 replies [Last post]
Richard Mann
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Apr 2016
Posts: 3
Groups: None

Hello,

I have a project on Asta that uses hammock tasks to summarise packages of work. I've been searching for a way to add a column that shows what hammock a task is assigned to; does anybody know if this is possible?

Any feedback would be greatly appreciated.

Thanks,

Rich

Replies

Charlotte Underhill
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 4 Jul 2016
Posts: 15

Hi Richard,

You can use the parent name colun which is found under the identification category.

Hope this helps :)

Mike Testro
User offline. Last seen 27 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Richard.

Just change the code of the new task.

Best regards

Mike T.

Richard Mann
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Apr 2016
Posts: 3
Groups: None

Thanks Mike, the only problem I have with that method is if I copy a task and it copies the code to the new task even though it's not allocated to the hammock of the original task. I wasn't sure if there was any other way of showing that the new task is not allocated to a hammock without doing it manually.

Mike Testro
User offline. Last seen 27 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Richard

Assign a code to each task and then assign the same code to the hammock.

Best regards

Mike T.