2 Ways to Create Level of Effort or Hammock Tasks in Microsoft Project

While Microsoft Project does not have a straight of the vbox Level of Effort activity type like primavera P6, you can still add Hammock or Level of Effort tasks to your Microsoft Project schedule, using one of 2 workarounds. 

The first workaround is the recommended method from Microsoft while the second method is one that is very common in the subsea construction world.

 