Show/calculate elapsed days between two tasks.

1 reply [Last post]
A. E.
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 31 Mar 2020
Posts: 2
Groups: None

Is it possible for ASTA to count the total number of days between two tasks? IE, I have an 'implement detour' and a 'remove detour' task at the beginning and end of my project respectiely, with tasks in between, and I need to know how many days the detour will be in place for. Can ASTA tell me this, or do I just have to count it myself? Thanks!

Replies

Paul Harris
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

You may use a Buffer Task and the calander that it is assigned to will be used to calculate the value of the gap.

Regards

Paul E Harris

Director Eastwood Harris

Publishers on Oracle Primavera, Microsoft project and Elecosoft (Asta)Powerproject books, videos and training material.