Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Elapsed days

1 reply [Last post]
Craig Adams
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71
Hello Fellow Planners,

I am filtering by critical path but seem to have some gaps!

Have found these are elapsed duration tasks - is there a reason Asta does not show these in a critical path?

Can any one tell me how to turn on so they show in path?

Kind regards,

craig Adams

Replies

Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4406
Hi Craig

Tasks with elapsed days are calendar day not work days.

If an ed task ends on a weekend or the middle of a holiday the next task on a workday will start on the next work day - leaving some float and therefore losing the critical path.

I only use elapsed days for a curing or drying out lead lag lead links.

If there is no real reason why the tasks should be on an ed calendar then change it to a work calendar.

Just switching the cell fortmat to work days will not solve the problem.

I have not yet discovered a work around for this small but irritating problem.

Best regards

Mike Testro