Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Permanent Resource - Calendar, Working Time, Overtime

1 reply [Last post]
Chris Lothian
User offline. Last seen 35 weeks 10 hours ago. Offline
Joined: 18 May 2007
Posts: 29

Hi all,

Is there a way to numerate total working time that a resource has been allocated, with separate figures for standard working time and overtime?

Currently I have a library of resources which i regularly use. I have duplicates of resources for those that work different calendars / times, but this is a bit disorganised and the library is oversized.

To solve this i was wondering if there was a way that you can allocate standard working hours to a resource, then when allocated to a task and if the task dictates the resource is required out of these standard hours this would be shown as overtime?

Chris

Replies

Ben Taunt
User offline. Last seen 8 hours 12 min ago. Offline
Joined: 16 Jan 2012
Posts: 88
Groups: None

Hi Chris,

I notice that you're using a fully supported licence of Asta Powerproject within your company - why not send this question directly to our support team so that they can help you?  They're committed to supplying a response within an hour so you'll get a faster turnaround that way:

UK Support Helpdesk: 01844 261609 or support@astadev.com

Best wishes,

Ben @ Asta