Calendar - 7 Day Working Week

1 reply [Last post]
Dominic Planner
User offline. Last seen 21 weeks 5 hours ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

I am creating a programme to completion that will require weekend working. 

I have set the calendar to 7 day working week but when I set an activity to work saturday and sunday, the activity bar jumps to the monday. 

How do I prevent this from happening?

Thanks 

Replies

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Dominic

Are you sure that you have set the calendar to 7 working days?

Also check that the calendar on your resource allocation is the same - it will over ride the plan calendar.

For instance if you have a gang of 3 carpenters - catholic - jewish and muslim - each with their own calendar you will only get 4 days work in the eek.

Best regards

Mike Testro