Histogram To Count Tasks
Mon, 2012-08-06 11:08
Hi All,
I'm trying to create a histogram that counts the number of Tasks at the instant in time that have a been alllocated with a cost centre value, rather unsuccessfully at the moment.
Does anyone know how?
Thanks,
Chris.
Tue, 2012-08-07 08:46
#1
Hi Chris
Alternatively create a dummy cost item at £1.00.
Best regards
Mike Testro
Mon, 2012-08-06 13:35
#2
Create a Dummy Resource, make it to be a non-leveling resource and assign a unit of this resource to all activities then the histogram for this resource shall display what you are looking for.