Civil Site Engineer, Suraj Kumar & Company, Buildings

START Date: 
July, 2002
END Date: 
March, 2004

• Carried out the periodic reviewing & monitoring the project progress with client and ensured the completion of project within the scheduled time and cost parameters. • Handled the bill preparation and checked Monthly Bill of Subcontractors.

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
2500

Civil Site Engineer, Biswas Engineering, Buildings

START Date: 
December, 2004
END Date: 
May, 2005
• Handled the preparation of daily & monthly progress report. • Developed & reviewed the project planning & progressing. • Reviewed the drawings, specifications and BOQ for speedy completion of work.
Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
400

Site Engineer, B E Billimoria & Company Limited, Residential Towers

START Date: 
May, 2005
END Date: 
November, 2005

• Carried out the quantity surveying works and monitored the execution of construction works. • Planned the daily works & responsible for client interactions. • Handled the sub-contractor bill preparation and checked Monthly Bill of subcontractors

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
800

Senior Engineer, Simplex Infrastructures Limited, Flyover Project

START Date: 
March, 2010
END Date: 
April, 2011
• Managed all activities in a timely manner including delivering study of drawing, scope and work specifications, preparation of base line schedule for the project and accurate updating of the project schedule • Created and implemented all functional schedules and S Curves in relation to Engg, procurement, construction and overall S Curve • Robustly delivered sale value calculations monthly for month-wise planned quantity as well as managing cost to completion, schedule of material requirement, employee requirements, labour needs and P&M requirements
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
900

Manager, Consolidated Construction Consortium Limited, Metro Railway Project

START Date: 
April, 2011
END Date: 
April, 2015
• Delivered comprehensive leadership support within this key railway project including the coordination, collation, verification and integration of the work scope into the project plan • Successfully identified and implemented all project milestones whilst analysing work activities to ensure milestone achievement • Created and assessed the schedule logic and duration in collaboration with the project team, ensuring all schedules were robustly managed • Completed comprehensive liaison on a multi-department basis, this maximised knowledge in relation to the project schedule requirements an
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
3200
Experience Hours (Forensic Analysis): 
4000