Area Planning Manager and Cost Manager, Larsen & Toubro, Ammonia Synthesis Gas Project

START Date: 
January, 2010
END Date: 
March, 2011
  • Preparing of Project Master Schedule by co-coordinating with all department like Engineering, Procurement & Construction using PRIMAVERA V.6 Software.
  • Preparing Project WBS, Project Planning Procedure, Progress Measurement Methodology & Project Co-ordination Procedure.
  • Prepare & updating L2, L3 Schedule for Project using PRIMAVERA V.6 Software.
  • Preparing Billing Schedule, Invoice & Cash Flow.
  • Tracking of Project by using <?xml:namespace prefix = st1 />SAPPS.
  • Development & updating

Programme Planner, Network Rail, Outer Areas - Thames Link Programme

START Date: 
December, 2007
END Date: 
May, 2009

December 07 – May 09                                         Network Rail

           Programme Planner