%100- Project Planning; Progress Reporting; Primavera P6; MSP

Assistant Planner or Planning Engineer, GEM Engserv Pvt. Ltd, 1.East Rail Corridor in the state of Chhattisgarh from Kharsia to Dharamjaygarh with a spur from Gharghoda to Gare Pelma:

START Date: 
April, 2018
END Date: 
January, 2021
  • Responsible for the preparation of Project schedules, Master Schedules, Look ahead Schedules using P6
    • Monitoring of schedules using P6.
    • Preparing schedule reports like critical activity report, near critical activity reports.
    • Supporting Manager and client in Delay analysis
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Forensic Analysis): 
100

Planner, GE Oil & Gas, Shop repair

START Date: 
September, 2017

Missions: Establish components repair planning.
Development and updating project reporting (qualification QMI & delivery).
Conducting meetings (weekly & monthly) with management.
Purchase orders request and goods delivery tracking.

Planning engineer, SARPI SPA, Tiguentourine

START Date: 
May, 2012
END Date: 
September, 2013

April 2013/ September 2013: Put at the disposal for the joint-venture SONATRACH /
BP / STATOIL, gas site of TIGUENTOURINE - AIN AMENAS. ALGERIA
Missions: Planning on MS PROJECT 2007.
Monitoring progress of the project (S-curve) and the development of resource histogram.
Development and updating of project reporting and attachments.
Conducting meetings (weekly & monthly) with the customer.

PROJECT ENGINEER, BST Services, Chachar Gas Plant Relocation Project, and so on,

START Date: 
April, 2013
END Date: 
November, 2014

JOB RESPONSIBILITIES

 

o   HAZOP Scriber for HAZOP Study under the supervision of HAZOP Chairman & developed HAZOP detailed Report

o   Project Scheduling in Primavera P6 & MS Project 2010

o   Controlling & Monitoring Project Schedule and Resource Loading & S-Curves

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
450
Experience Hours (Forensic Analysis): 
300

Planning Engineer, Pipelink Construction (Pvt) Limited, Installation of 12", 6" & 4" x 170 Km of Pipeline and 30 Nos. of Wellhead Work Project

START Date: 
December, 2014

At PCL Headoffice:

·         Tender’s Evaluation

·         Project Scheduling in Primevera P6 & MS Project 2010 for Bids

·         Resource Loading& S-Curves

·         Costing Assistancy in Projects

·         Labor & Equipment Histograms

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
300

Project Planner, 1) Carillion plc, UK Power Networks

START Date: 
January, 2009
END Date: 
December, 2015

Industry - Utilities

UKPower Networks

Substation Refurbishment Project

 

Experience Hours (Planning & Scheduling): 
14000
Experience Hours (Cost Management): 
14000

Senior Projects Planner, Skanska Plc, North West Cambridge Development

START Date: 
June, 2003

A range of Planning roles from RIMINI Planning to Senior Project Planning, across a multitude of sectors.

Experience Hours (Planning & Scheduling): 
2600
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
650

Assiatant Manager Planning, ITC Limited, Industrial Food Factory

START Date: 
June, 2014
The AccountabilitiesPlanning:Development of Project specific WBS, Master Program for “Greenfield & Brownfield” project and consolidating various sub-contractors program to achieve required deliverables & milestones.Tracking and reporting on statutory approvals’ compliancePreparing and tracking Tender Event Schedule, floating of tender, PQ, Checklist, participating in tender negotiation meeting with various sub-contractors/vendors.Review and approval of Contractor’s schedule in-line with master program, Extension Of Time Claims
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
600

Assiatant Manager Planning, ITC Limited, Industrial Food Factory

START Date: 
June, 2014
The AccountabilitiesPlanning:Development of Project specific WBS, Master Program for “Greenfield & Brownfield” project and consolidating various sub-contractors program to achieve required deliverables & milestones.Tracking and reporting on statutory approvals’ compliancePreparing and tracking Tender Event Schedule, floating of tender, PQ, Checklist, participating in tender negotiation meeting with various sub-contractors/vendors.Review and approval of Contractor’s schedule in-line with master program, Extension Of Time Claims
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
600

Planning Engineer, Chirag Group Of Companies, 2B+G+14 Hotel Building,G+4P+10 Residential Building,G+1P+10 Residential Building

START Date: 
December, 2015

*Preparing Baseline Program

*Preparing Cash Flow

*Preparing Manpower Curve & Histogram

*Preparing Recovery Program

*Preparing Updated Program

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500