Norway (EU.NO)

Operations & Maintenance Planner – Oil Production, Maersk FPSOs, Maersk Inspirer - Volve Field

START Date: 
January, 2008
END Date: 
May, 2010

 Developed and introduced an updated Operations based planning process with associated Work Breakdown Structure for Maersk Inspirer / Volve Field Development. • Responsible for all operations, shutdown and major maintenance planning for Maersk Inspirer (Statoil Volve Project) using Microsoft Project 2003. • Close liaison with Volve Project Team to ensure a smooth handover to the Operations phase.

Experience Hours (Planning & Scheduling): 
4000

Onshore Asset Planner, Marathon Oil Norge AS, Alvheim FPSO

START Date: 
May, 2010
END Date: 
October, 2012

Onshore Asset Planner, Alvheim FPSO - Maintenance, Operations & Turnaround Planning for the Alvheim FPSO. SME for planning in Operations group

Experience Hours (Planning & Scheduling): 
2800

Senior Planner, Det norske Oljeselskap ASA, Multiple Projects - Green & Brownfield Developments

START Date: 
October, 2014
END Date: 
October, 2016

Senior Planner - Projects Transferred from Marathon to Det norske after aquistion of MONAS assets. Part of Project Controls function within the Projects Business Unit NoA Development Project – Asset Team & Facilities Team Part of Alvheim Asset early phase team Provide planning support to Alvheim Area Projects Developed Company Standard Work Breakdown Structure to be used in all Projects Responsible for Schedule & Cost Risk analysis using Primavera Risk Analysis (Pertmaster) Revised Governing Documents for Planning Function Planning support to all DETNOR Business units

Experience Hours (Planning & Scheduling): 
4000

Senior Planning Engineer, Kvaerner Engineering Norway, Norsk Hydro Oseberg Project

START Date: 
July, 1984
END Date: 
May, 1985

A member of the Project Surveillance team responsible for the planning and reporting function based at Stavanger Module Fabrication Site.

Experience Hours (Planning & Scheduling): 
1750

Oil & Gas Senior Planning Engineers - Primavera, Aker Solutions, Johan Sverdrup

START Date: 
January, 2012

Senior Planning Engineer - At Aker Solutions Engineering & Technology AS

 

 Position: Senior Planner - Engineering department

 Responsabilities: Engineering planning:

-Maintaining, updating and issuing weekly reports for Contract Baseline Schedule, manpower  histograms, by discipline and Cost-Time-Resources scope.

Experience Hours (Planning & Scheduling): 
11850

Project Planning Engineer, Aker Solutions, Vigdis Nordøst; Kaombo Block 32 SPS Project

START Date: 
March, 2012
END Date: 
August, 2016
Planning for Subsea projects with tasks including but not limited to:- Preparation, update and follow up of schedules for EPC of Subsea production systems- Preparation of bi-weekly and monthly reports for internal management and the client (S-curves, progress figures, detail schedule and forecast delivery dates)
Experience Hours (Planning & Scheduling): 
8500

Engineering Planner, Aker Solutions, MMO -Snorre /Gullfaks

START Date: 
October, 2010
END Date: 
March, 2016

 As Sr.Planning Engineer-Projects

Experience Hours (Planning & Scheduling): 
9600

Engineering Planner, Aker Solutions, MMO -Snorre /Gullfaks

START Date: 
October, 2010
END Date: 
March, 2016

 As Sr.Planning Engineer-Projects

Experience Hours (Planning & Scheduling): 
9600

Planning and Project Control Engineer , Società Italiana per Condotte d'acqua, Oslo Norway, Drill&Spilt Tunnel Cosntruction Project

START Date: 
April, 2015
END Date: 
February, 2016

·     Developed, control & update the overall planning/work program, using Primavera P6.

·     Supervise, monitor & update the actual construction progress and compare to our planned progress in order to point out the performance and the criticality of the schedule.

·     Monitor and update the manpower forecast and progress.

Ertan Ozturk

First Name: 
Ertan
Last Name: 
Ozturk

Cost estimation, Cost-to-complete forecasts, Cost budget tracking, Cash flow estimation, Trends, Unit price calculation

Schedule estimation, Progress tracking

Manpower planning, equipment planning

Reporting (daily, weekly, monthly report cycles)

Professional Since: 
Jul-2002 (21.8 yrs experience)
Oldest experience: 
Jul 2002 (21.8 yrs experience)
Years Experience: 
13