BERREKIA Mohamed Nacer

First Name: 
BERREKIA
Last Name: 
Mohamed Nacer

 

A total of 14 years experienced in Construction Industry and Oil & Gas Operations (including 7 years in Engineering/Procurement/Construction), A combination of 14 years in Algerian desert (South of Algeria)  in Gas/Oil Refinery & Petrochemical Plant. Directly involved in the Project Planning and Controls using the latest version of Primavera Project Planner (P3 & P6) and MS Office.

Professional Since: 
Apr-2010 (15.3 yrs experience)
Oldest experience: 
Jan 1999 (26.6 yrs experience, WARNING: 11.2 years variance with Professional Since)
Years Experience: 
13

Technical Department Chief & Project Manager, GCB / Sonatrach, In Amenas all area Project

START Date: 
April, 2006
END Date: 
March, 2010

 

GCB/Sonatrach                                             Technical Department Chief & Project Manager

Planning & Technical engineer, VINCI Construction Grands projets , SkiKDA New LNG Train

START Date: 
December, 2010
END Date: 
June, 2009

Planning & Technical engineer:

-Maintain project planning updates.

-Daily/Weekly/ Monthly report redction.

-Assist to the project deputy manager/tecnical manager/quality manager,

-BOQ updates

gssgg sgsgsdgs

First Name: 
gssgg
Last Name: 
sgsgsdgs
Professional Since: 
Mar-1985 (40.4 yrs experience)
Years Experience: 
0

Software instructor, COSIDER, (various projects)

START Date: 
June, 2011
END Date: 
January, 2011

Primavera P6 instructor for more than one hundred civil works engineers in the largest building and public works company in Algeria

Chef Planning & Methode, ANADARKO ALGERIA COMPANY LLC, Hassi Berkine

START Date: 
March, 2003
END Date: 
October, 2002

Head the Planning & Methodes Department for Groupment Berkine in Hasi Berkine to take the Central Processing Facilities from construction phase into operations phase.  Contract not renewed due to Alegerianisation of the position which operated on a back-to-back basis with another UK national 

Planning & Cost Engineer, Hess Corporation, GASSI EL AGREB ALGERIA

START Date: 
March, 2007
END Date: 
April, 2005

Planning and Cost Engineer for Amerada Hess on El Gassi, Zotti and El Agreb Fields in Algeria.  Interface with the contractor (Bechtel) on the GCR Project at Zotti. The GCR Project is for the EPC of a green-field plant to facilitate Automated Central Well Wash to all wells in all three fields and the enhanced Gas Lift and Gas Injection on the El Gassi Field.  GEA is a mature field operation with the output having depleted to 20,000bbl.

Piero Capello

First Name: 
Piero
Last Name: 
Capello
Professional Since: 
Aug-1999 (26.0 yrs experience)
Oldest experience: 
Jan 1996 (29.6 yrs experience, WARNING: 3.6 years variance with Professional Since)
Years Experience: 
16

Project Control Manager, Saipem SpA, GNL3Z Arzew. Algerie

START Date: 
June, 2009

Project Control Manager at GNL3Z Arzew Project. 4Billion eueq, 15Million MHrs standard, 40Million MHrs Spent, 11k MPower, 800 project team members, 12 Project Management Team, 26 Project Control team members, 6 nationalities, 48 Months construction phase.

aymen teffahi

First Name: 
aymen
Last Name: 
teffahi

COST CONTROL AND PLANNING IN ALGERIAN PIPING PROJECT WITH PRIMAVERA

Professional Since: 
Aug-2010 (14.9 yrs experience)
Oldest experience: 
Aug 2010 (15.0 yrs experience, WARNING: 0.1 years variance with Professional Since)
Years Experience: 
42