PLANNING ENGINEER, "ANABEEB CO. LTD, Saudi Arabia", Plant shutdown maintenance

START Date: 
April, 2013

1.) Assists in the preparation of Project Execution Schedule including resource allocation based on project contractual requirement.
2.) Performs staff functions regarding Project Schedule, Physical Accomplishment and activity sequence.
3.) Develops a well defined and properly sequenced work activities in close coordination with the PM/PIC;
4.) Initiates and facilities the development and maintenance of the project schedule;
5.) Inspects the project site and coordinates changes in project schedule;

Acting Planning Manager, Doosan Babcock, Plant shutdown maintenance

START Date: 
July, 2009
END Date: 
October, 2009

In July 2009 I was sent out to Trinidad to work on a project there for 3 months.  The team consisted of two Mechanical Engineers and me. 

All planning was carried out by me; after the planning was complete I took the role of supervisor.  

In my training I took part in several SMTD courses (Supervisor and Management Training Development)

I also have a license for fork lift operation and a safety passport.

In July (12th to the 14th) I was on a Primavera (P6) training course which I now have a certificate for.

Trainee Planner / Technical Assistant, Doosan Babcock, Plant shutdown maintenance

START Date: 
September, 2008
END Date: 
December, 2009

I spent from September 2008 to December 2009 as a Trainee Planning Engineer for Doosan Babcock. 

During my employment which ended due redundancy I took on several projects. 

While working in Cockenzie Powerstation (East Lothian) I ran and maintained a full unit shutdown as well as getting contracted to refurbish pipework in a distillery in Edinburgh.  As well as these I ran basic maintained work on the station.

PLANNING ENGINEER, KPO b.v., Plant shutdown maintenance

START Date: 
May, 2009

Planning Engineer  

- Implementation and preparation of Units shutdown planning, planned preventive and corrective maintenance, opportunity based planning, campaign maintenance and development planning.

- Development of reports, monitoring progress against plan.

- Tracking the list of material delivery for shutdown activities in support of the planning activity (Bookies board).

- Prepare the 4 weeks look ahead integrated plan,3 days look ahead during shutdown

- Major