PLANNING ENGINEER, "ANABEEB CO. LTD, Saudi Arabia", Plant shutdown maintenance

START Date: 
April, 2013

1.) Assists in the preparation of Project Execution Schedule including resource allocation based on project contractual requirement.
2.) Performs staff functions regarding Project Schedule, Physical Accomplishment and activity sequence.
3.) Develops a well defined and properly sequenced work activities in close coordination with the PM/PIC;
4.) Initiates and facilities the development and maintenance of the project schedule;
5.) Inspects the project site and coordinates changes in project schedule;
6.) Analyzes all contract data, establishes well-defined work activities and creates a comprehensive properly linked CPM schedule;
7.) Understands the flow and logistics needed for the execution of the project activities;
8.) Organizes large amounts of information into a coherent and meaningful P3/P6 format;
9.) Operates the Primavera (3/6) scheduling software;
10.) Prepares all related information needed to support the field operation requirement as far as construction schedule is concerned.