Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

(LUL/Metronet Affiliates Project) London

Planner, PMPS Ltd, (LUL/Metronet Affiliates Project) London

START Date: 
January, 2014
END Date: 
March, 2018

Different projects under PMPS Ltd

Key Responsibilities

  • Update schedule in weekly basis
  • Producing look ahead programme
  • Supporting the Senior planner by providing accurate levels of progress, monitoring and managing change control process and baselines, and ensuring general accuracy of information in P6 in line with internal standards and procedures.
  • Analyze critical path to determine changes to schedule
  • Gather / analyse the programme update information (physical % and end dates) to help updating programme.
Experience Hours (Planning & Scheduling): 
5000

Planner, Clancy Docwra, (LUL/Metronet Affiliates Project) London

START Date: 
April, 2018

Roles and Responsibilities: Currently managing and updating TF1021 – Ealing Common Depot – Civil Works Package – Construction Programme, TF1023- Ampere Way Retaining Wall Works Construction Programme.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
100

Project Planner, Metronet Atkins Station Design Team, (LUL/Metronet Affiliates Project) London

START Date: 
February, 2003
END Date: 
February, 2005

Metronet (ASDT)                                                                                                &nb

Assistant Planning Manager, Metronet Alliance, (LUL/Metronet Affiliates Project) London

START Date: 
March, 2006
END Date: 
January, 2008

Metronet Alliance                                                   Senior Planner / Assistant Planning Manager

Planning Engineer, Engenica, (LUL/Metronet Affiliates Project) London

START Date: 
January, 2003
END Date: 
December, 2003

Producing a fully detailed, resourced and cost allocated programme from project inception, monitoring progress against programme throughout the project lifecycle, and producing reports for use by both the project teams and senior management on the current London Underground Station Modernization Programme. I was involved in Planning all BCV (Bakerloo, Central and Victoria lines) and SSL (all other lines except Jubilee and Northern Lines).

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content