Lead construction planner

Lead Construction Planner, BECHTEL, CADP- London City Airport Developement Project

START Date: 
September, 2017
END Date: 
May, 2020

I was responsible for setting up the structure in the project controls team and allocate the planners/contract admins depending on their skill level, experience and got the best of their abilities to develop the project programmes and cost control reports and phasing schedules for this complex project.

 

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Lead Construction Planner, Lycopodium Engineering Pty. Ltd., Ahafo Gold Project

START Date: 
November, 2004
END Date: 
February, 2006

Responsible for all site construction planning activities for the Ahafo Gold project

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
500

Lead Construction Planner, Worley Parsons, Hebron

START Date: 
August, 2011

 

2011 - Present

Planner, WorleyParsons, Houston, TX

ExxonMobil – Hebron Topsides Project, Offshore Newfoundland.

Lead construction planner / scheduler responsible for the following (but not limited to):

  • P

Lead construction planner, SMNM-VECO, North Gas Transfer Terminal, Sakhalin 2

START Date: 
February, 2011
END Date: 
August, 2011

 

1.      Head of the Project Planning Department ( Managing and Monitoring all Scheduling activities of the Project and cost recording)

2.      Developing Master Schedule (work in the Company head office and on site)

3.      Developing Work Execution Schedule

4.      Coordination with the Client for implementation of the Client’s requirements

5.      Determine Resources for planned works

Lead construction planner, United Construction Management Company (construction supervision services), RESIDENTIAL & COMMERCIAL BUILDINGS

START Date: 
September, 2009

Develop, monitor and update schedules for company's construction and engineering projects in Krasnodar, Gelendzhik and Sochi cities

Lead construction planner, Network Rail, High Output System 4, BCS & TRS Acquisition and Commission

START Date: 
April, 2008
END Date: 
February, 2010

April 2008-Present
Network Rail IMT (RAIL S&C Track Renewals – Birmingham/Manchester/York)
- High Output System 4, BCS & TRS Acquisition and Commission - LNE and LNW. Principal Project Planning Engineer.
- Lead Planner responsible for maintaining Network Rail LNW S&C Design Programmes and KPIs, (Contractors include: Jacobs, Atkins, Scott Wilson, Arup, Corus).
 