Duco Ltd (Part of Technip Group)

Manufacturing Planner, Duco Ltd (Part of Technip Group), Multiple Clients

START Date: 
September, 1997
END Date: 
June, 1998

 

<

Manufacturing Planner

The role combined some duties of a Project Planner, but my main responsibility was controlling the Manufacturing workload throughout the factory.  Procurement of raw materials, advising the Production Manager and other departments of daily manufacturing priorities / activities.  Attending daily production meetings to review production performance, solve Logistical problems.

Logistics Engineer, Duco Ltd (Part of Technip Group), Agip Safueiro, BG maria, Burullus Simian / Sapphire, Chevron Kuito, Shell Pohokura, Shell Saderi, Shell Serai, Total AKPO HFL's

START Date: 
September, 1997
END Date: 
May, 2006

Areas of Responsibility: Logistics Engineering.

Role Responsibilities:

  • Duties include the co-ordination / management of manufacturing activities from contract award to loadout.  This includes engineering review and analysis of non-conformance reports, facilitation of technical review meetings and control of project costs including variation orders.  Co-ordinating fitting of hardware and final testing inline Duco’s Quality systems, ISO9001 and API requirements.

Project Engineer, Duco Ltd (Part of Technip Group), Petro SA South Coast Gas, Talisman Duart, Cameron Husky HFL's

START Date: 
May, 2006
END Date: 
February, 2007

Areas of Responsibility: Project Engineering

Role Responsibilities:

  •  Working in a project team, responding to a Project Manager, duties included review and interpretation of client specifications; generating specific project deliverable drawings and documents in line with client specifications; liaising with manufacturing to provide relevant information to produce umbilicals and associated hardware on time and within budget, ensuring both quality and reliability.
  • Advising project status and rep

Logistics Supervisor, Duco Ltd (Part of Technip Group), Chevron Agbami, PDVSA Dragon HFL's, Vetco Gray Kipper Tuna

START Date: 
February, 2007
END Date: 
October, 2007

Supervising a small team of four Logistics Engineers in controlling the umbilical manufacture within the Manufacturing facility.

  • Performing the duties of a Logistics Engineer:
  • Engineering review and analysis of non-conformance reports, facilitation of technical review meetings and control of project costs including variation orders.  Co-ordinating fitting of hardware and final testing inline Duco’s Quality systems, ISO9001 and API requirements.

Logistics / Planning Manager, Duco Ltd (Part of Technip Group), BP Andrew Kinnoull, BP Skarv, Chevron Agbami, Encana Deep Panuke, Mearsk Dumbarton & Lochranza, Murphy Azurite, Talisman Auk North, Total Islay

START Date: 
October, 2007
END Date: 
July, 2011

Areas of Responsibility: Project / Manufacturing & Applications Planning, Logistics Engineering and Project Shipping.

Role Responsibilities:

  • Overseeing tender plans and project planning to ensure that the requirements of the client are achieved.
  • Overall planning management of the factory ensuring the factory runs at optimum capacity.
  • Ensuring umbilicals are manufactured and tested in line with the client’s specifications and to ISO systems.
  • Strategic monthly forecasting for production man-hour requirements, machine capacity, and rev

Market Place