Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Chevron

Cost and Planning Engineering Analyst, Chevron, GORGON LNG Project

START Date: 
March, 2006
END Date: 
January, 2007

1. Cost and Planning Engineering Analyst – Gorgon Expansion Project

·       Development of the Downstream Cost Model for the proposed Expansion Project, which would take the project beyond the years 2009 until 2020.

Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
1200
Experience Hours (Forensic Analysis): 
500

Cost and Planning Engineer, Contracts Engineer, Chevron, Eni, Exxon, RasGas, Zakum Development Company (ZADCO), Various Projects in U.S., Central Asia, Middle East and Africa

START Date: 
April, 1982
END Date: 
December, 2015

I've held various roles in project controls and contract management in the international oil and gas industry; pls see my LinkedIn profile for details

Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
20000

Fernando Cruz

First Name: 
Fernando
Last Name: 
Cruz

     I have thirteen (13) years of professional experience, 11 of 13 in project management (mainly: projects, contracts and planning management areas) in Oil, Gas & Energy related to the supply of subsea equipment and services onshore / offshore, VLCC conversion to FPSO P-74, Suction Piles fabrication of P-55, Living Quarter fabrication of the DRU-01 for Setebrasil, EPC Contracts of topside modules construction for offshore platforms: P-52, P-51, PRA-1, P-53 and P-56 Generation or Compression Modules in the following companies: Superpesa Industrial, Wellstr

Professional Since: 
Sep-2003 (20.6 yrs experience)
Oldest experience: 
Sep 2003 (20.6 yrs experience)
Years Experience: 
12

Planner, Chevron, Gorgon Project

START Date: 
May, 2007

Planner on the Chevron Gorgon Project. A 50Billion+ AUS mega project in the Oil and Gas Industry. Project encompasses a 2 field, 20 drill offshore field tie'd back to a LNG plant to be built on Barrow Island, a class A nature reserve and then linked to mainland Australia via another pipeline.

Kevin Matthews

First Name: 
Kevin
Last Name: 
Matthews
Oldest experience: 
May 2007 (16.9 yrs experience, WARNING: 37.3 years variance with Professional Since)
Years Experience: 
43

Planner, Chevron, Gorgon Project

START Date: 
May, 2007

Planner on the Chevron Gorgon Project. A 50Billion+ AUS mega project in the Oil and Gas Industry. Project encompasses a 2 field, 20 drill offshore field tie'd back to a LNG plant to be built on Barrow Island, a class A nature reserve and then linked to mainland Australia via another pipeline.

Planner, Chevron, Gorgon Project

START Date: 
May, 2007

Planner on the Chevron Gorgon Project. A 50Billion+ AUS mega project in the Oil and Gas Industry. Project encompasses a 2 field, 20 drill offshore field tie'd back to a LNG plant to be built on Barrow Island, a class A nature reserve and then linked to mainland Australia via another pipeline.

Planner, Chevron, Gorgon Project

START Date: 
May, 2007

Planner on the Chevron Gorgon Project. A 50Billion+ AUS mega project in the Oil and Gas Industry. Project encompasses a 2 field, 20 drill offshore field tie'd back to a LNG plant to be built on Barrow Island, a class A nature reserve and then linked to mainland Australia via another pipeline.

Colin Davis

First Name: 
Colin
Last Name: 
Davis
Professional Since: 
Aug-2003 (20.7 yrs experience)
Oldest experience: 
Jun 2003 (20.8 yrs experience, WARNING: 0.2 years variance with Professional Since)
Years Experience: 
10

Senior Planner, Chevron, LNG Plant - WHEATSTONE Australia: owner Chevron

START Date: 
June, 2013

Too much to list, too many requirements before access to tabs