Most Recent Forum Discussions

Post Title Replies Last Updated
Preferred progress Measurement Technique
Planning, Scheduling & Programming Discussion
1 Rafael Davila
3 min 9 sec ago
nasiona marihuany sklep stacjonarny
TURNAROUND & SHUTDOWN (T/A & S/D)
0 Kilian Puchała
5 hours 58 min ago
MSP: Elapsed total float ignored - even when increasing threshold for critical tasks
Microsoft Project
3 Tom Boyle
12 hours 5 min ago
Cash Flow report without resource loading in P6
Oracle Primavera - PM6
8 Zoltan Palffy
12 hours 33 min ago
Submittals, Resubmittals, and More Resubmittals
Oracle Primavera - PM6
4 Zoltan Palffy
12 hours 34 min ago
Totals in Original Duration Column giving wrong figure
Oracle Primavera - PM6
10 Zoltan Palffy
12 hours 42 min ago
two accounts
Improving Planning Planet Website
14 PP Admin
16 hours 46 min ago
Piping activities
Planning, Scheduling & Programming Discussion
0 Muhammad Ahmad
2 days 16 hours ago
Baseline in Primavera
Oracle Primavera - PM6
8 Rafael Davila
2 days 22 hours ago
converted PowerProject programme mixed duration formats
Microsoft Project
1 Tom Boyle
3 days 4 hours ago
Programme Forecast
Planning, Scheduling & Programming Discussion
4 Mike Testro
3 days 10 hours ago
Project management
Planning, Scheduling & Programming Discussion
3 Zoltan Palffy
3 days 12 hours ago
Retaining Activity ID logic
Planning, Scheduling & Programming Discussion
1 Zoltan Palffy
3 days 12 hours ago
New Primavera 17.12.1 set-up with SQL 2014
Oracle Primavera - PM6
9 Zoltan Palffy
3 days 12 hours ago
MSP: Elapsed total float ignored - even when increasing threshold for critical tasks
Microsoft Project
0 Henrik I
3 days 15 hours ago
4D Planning for Turnarounds and Shutdowns
Building Information Modelling (BIM)
3 Jaishankar Pandey
4 days 8 hours ago
Inexusable Delay
Project Management Issues Discussion
4 Zoltan Palffy
4 days 12 hours ago
[Q] Changing External Project Relationship to another project?
Oracle Primavera - PM6
1 Zoltan Palffy
4 days 12 hours ago
Cannot import MPP files to Primavera P6 V7.0
Oracle Primavera - PM6
26 Zoltan Palffy
4 days 12 hours ago
Is there a consensus for the best practice for implementing a revised baseline for a schedule that has already been progressed?
Oracle Primavera - PM6
8 Zoltan Palffy
4 days 12 hours ago
New software for 5D modelling using BIM
Building Information Modelling (BIM)
7 Vladimir Liberzon
5 days 4 hours ago
P6 SDK: Activity6v6.xls work partially after to upgrade Primavera P6 8.3 to 8.3.15
Oracle Primavera - PM6
7 Zoltan Palffy
1 week 12 hours ago
Resource lookahead
Planning, Scheduling & Programming Discussion
6 Zoltan Palffy
1 week 12 hours ago
Boq and drawing related
Project Management Issues Discussion
2 Muhammad Ahmad
1 week 2 days ago
P6 R8.1 "Printer Selected is Invalid"
Oracle Primavera - PM6
8 Brother Error ts-02
1 week 2 days ago
change asta calendar
Asta Powerproject
5 Mike Testro
1 week 3 days ago
Impact of Global calendar vs Activity based calendar
Planning, Scheduling & Programming Discussion
3 Zoltan Palffy
1 week 4 days ago
Importing Microsoft Project (XML) to P6
Oracle Primavera - PM6
1 Zoltan Palffy
1 week 4 days ago
RISK TYPE Data in exported file
Oracle Primavera - PM6
5 Solamon T Varghese
1 week 4 days ago
Budgeted Labor Units
Oracle Primavera - PM6
1 Zoltan Palffy
1 week 6 days ago
BL Duration % Complete
Oracle Primavera - PM6
3 Zoltan Palffy
1 week 6 days ago
Manpower Budgeted Time is Changing
Oracle Primavera - PM6
3 Zoltan Palffy
1 week 6 days ago
Five Critical Responsibilities for Successful Project Management
Project Management Issues Discussion
0 Alex Carter
2 weeks 6 hours ago
Cumulative S-curves:
Oracle Primavera - PM6
12 Rafael Davila
2 weeks 12 hours ago
the case for and against putting a Float Activity at the end to keep critical path zero for simplicity etc.
Oracle Primavera - PM6
1 Zoltan Palffy
2 weeks 12 hours ago

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes