Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline/Updated program of works

No replies
Khawaja Ahtisham
User offline. Last seen 40 min 5 sec ago. Offline
Joined: 15 May 2025
Posts: 3
Groups: None

Hi All

I have query that I have recieved Main Contractor Program of works as first program during the execution of project with Baseline dates and Updated/Revised dates together,Program of works also carrying -36 days TF,

I am claiming this program with udated dates as a Baseline program for us with responsibility of -ve TF under Main Contractor...

Is my claim justified !!!or there is better way to handle thesituation !!!!

The program of works fil is provided in pdf format only.

Regards

Khawaja