MPX Import Error

No replies
Phil Bedford
User offline. Last seen 16 weeks 3 days ago. Offline
Joined: 23 Jun 2016
Posts: 20

Hi,

Im attempting to import an MSP file in to P6.

I have exported as an xml (after checking for blank lines and summary tasks etc) but the file doesnt open in P6.

I have converted the mpp to mpx and then tried to import - however, I get the following error:

 

Im assuming the error is the ORA-01400 cannot insert null into.... but I really dont know where to look in MSP to find the issue.

Any assistance would be really appreciated.

Zoltan Palffy
User offline. Last seen 1 week 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

there is only one program that I found that can do this correctly than that is 

xertransfer

https://www.xertransfer.com/

this is an addin utility ot MSp and you can convert to P6 from MSP or to MSP from P6

it even lets you map fields 

everyone program that I used did not convert correctly.