Senior Planning Engineer, Shimizu, Taisei, SK E&C, Mass Rapit Transit Project - Construction of Station and Tunnel

START Date: 
August, 2006

CAREER HISTORY

1)  SK E&C (Singapore Branch)

     (Downtown Line MRT Stage 3 Contract 930 – Singapore)

      Contract Value – SGD 106.7 millions

     Planning Engineer / Scheduler (May 2011 – Present)                                                 

  • Preparation of Baseline Programme including the cost loading, resource loading, progress and cashflow S-curve for the project based on the Client’s working drawings and specification. The project is awarded on 01 April 2011.
  • Preparation of Montly Progress Report (including Progress Photograph) for submission to the Client.
  • Progress update and weekly monitoring of the progress and updating Project Critical Path
  • Monitoring and Analysis of Project Critical Path
  • Providing Catch-up schedule for construction works.

  

2)  Shimizu Corporation

(Downtown Line MRT Stage 1 Contract 905 - Singapore)

Contract Value – SGD 102.7 millions

      Snr Planning Engineer (Sep 2007 – Apr 2011)

-   Preparation of Project Baseline Programme including the cost loading, resource loading, progress and cashflow S-Curve

  • Progress updating and preparation of 3-month rolling schedule and monthly reporting to Client (LTA)
  • Liaise with site managers and subcontractor for the preparation and maintenance of  weekly schedule
  • Preparation of necessary follow up schedule such as interface schedule with other contractors and GP Formula 1 organiser, catch-up programme, etc.
  • Assist in providing necessary information to substantiate claims and EOT.
  • Monitoring and updating tunneling progress and datas
  • Preparation and updating of Risk Assessment for the project.
  • Provide baseline programme for several tender submissions.

 

 3)  Taisei Corporation

(Circle Line MRT Stage 4 & 5 Contract 854 - Singapore)

Contract Value – SGD 391 millions

 Senior Engineer (Nov 2006 – Aug 2007)

-  Preparation and maintenance of method statement for construction of station and cut and cover tunnel

  • Progress reporting for weekly and monthly updates as well as feedback for Monthly Report for submission to Client
  • Preparation and update of construction schedule.
  • Liaising with Consultants to solve technical problems
  • Coordination for Permit to Excavate and Temporary Works

 

 

4)  SembCorp Engineers & Contractors Pte Ltd

      Project C856 – MRT Circle Line Stage 5

Civil Engineer (Aug 2006 – Nov 2006)

Contract Value – SGD 335 millions

 

  • Assisting Design Manager in Consultant’s coordination matter, technical issues and queries, etc.
  • In charge of shop drawings preparation and checking for diaphragm wall construction for 5 MRT stations

 

Project C422 – Kallang Paya Lebar Expressway

QA/ QC Engineer and Instrumentation Engineer (2002 – Aug 2006)         

Contract Value – SGD 257 millions

 

  • Overall control of all QA/QC matters.
  • Preparation, monitoring and ensure the implementation of Quality Plan and Quality Management System.
  • Liasing with Company Quality Assurance Department on quality issues.
  • In-charge of Drawing Issue and Control and maintenance of controlled documents.
  • Preparation and maintenance of construction method statements and material submission.
  • In-charge of Instrumentation and Monitoring
  • Assisting Design Manager in consultants’ coordination matters & some technical issues, technical queries, submission of Permit to Excavate, etc.
  • Prepared Monthly Progress Report for submission to Client
  • In-charge of as-built submission to Client
  • Internal auditor for the company.

  

4)  Kumagai – Sembawang – Mitsui Joint Venture

(North East Line MRT C705 - Singapore)

Civil Engineer (Aug 2000 – 2002)

 -  Material quantity (especially for reinforcement bar) calculation, ordering & issuing. Provide re-bar bending schedule & details.

  • Metal or timber formwork & falsework system design and arrangement.
  • Construction concept & method statement preparation & submission to client (LTA).
  • Study and understanding Architectural & Structural drawings.
  • Preparing the schedule and progress report system, i.e. Two weeks rolling schedule, Weekly Progress report and Monthly Progress report.
  • Preparation  and submission of the structural plans to Authority
  • Preparation and submission of as-built drawings to Authority and Client (LTA).
  • Coordinating with Structural Professional Engineer and Accredited Checker.
  • Towards end of project, took over the Public Relation task and work involved such as entertaining complains and enquiries from Town Council and residents.