Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Network Rail

Project Planner, Network Rail, Various

START Date: 
September, 2009

Planner for Network Rail in Derby.

Working on various projects on the Midland Mainline and East Midlands areas.

Simon Martin

First Name: 
Simon
Last Name: 
Martin
Professional Since: 
Mar-2008 (16.1 yrs experience)
Years Experience: 
0

Track planner , Network Rail, Cross Rail

START Date: 
November, 2010
END Date: 
April, 2010

Experience

infrasteucture Junior Planner cross Raill Planning and scheduling reporting

Gantt chart Inprovement

J S A

First Name: 
J S
Last Name: 
A
Professional Since: 
Sep-2001 (22.6 yrs experience)
Years Experience: 
0

Project Planner, Network Rail, National Telecommunication Programme Office

START Date: 
August, 2005
END Date: 
September, 2007

 Achievements

  • Coordinated and Supervised a team of 8 planners to create and implement an involved Level 4 Interproject Relationship Programme consisting of 70 000 activities with a complex Work Breakdown Structure for Network Rail’s Railway Communications System Programme. 
  • Responsible for the Cost & Resource Loading for the Southern UK Regions portion of the £1.27 billion programme.
  • Shared responsibility for general project control spanning several projects within a large programme.
  • Lead a team of 4 planners to maintain and update

Project Planner, Network Rail, Civils East Anglia Upgrades

START Date: 
April, 2006
END Date: 
March, 2007

 Project Planner on Civils East Anglia Framework Contract for Network Rail

 

  • Responsible for salvaging a project work bank of around 100 live civil engineering projects using P3e.
  • Creating cost loaded plans with complete logical dependencies, baselines for monitoring/evaluation, complete WBS coding structure, critical paths and physical progress measures.
  • Producing recovery programs to ensure project critical milestones are met on time.
  • Creating and managing a monthl

TASS Data Technician, Network Rail, West Coast Modernization Route

START Date: 
March, 2002
END Date: 
March, 2005

TASS Data Technician for Network Rail producing completion certificates and updating strategic programme in P3 for the West Coast Mainline project.  Also assisted in carrying out gauge clearance analysis for the Pendolina KE8 train.

Area Planning Manager, Network Rail, West Coast Modernization Route

START Date: 
July, 2004
END Date: 
June, 2005

Develop and monitor in weekly basis the North West integrated Schedule for the West Coast Railway Modernization Project  (2,5 billion £).

Ian Reid

First Name: 
Ian
Last Name: 
Reid
Professional Since: 
Mar-2005 (19.1 yrs experience)
Oldest experience: 
Aug 2009 (14.7 yrs experience, WARNING: 4.4 years variance with Professional Since)
Years Experience: 
1

Ketan Patel

First Name: 
Ketan
Last Name: 
Patel
Professional Since: 
May-2008 (15.9 yrs experience)
Oldest experience: 
Jul 2009 (14.7 yrs experience, WARNING: 1.2 years variance with Professional Since)
Years Experience: 
1

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content