Network Rail

Stephen Edwards

First Name: 
Stephen
Last Name: 
Edwards

I am a highly motivated construction professional with experience of working within major programmes of work, able to work at all levels of organisations.

By identifying and working with key stakeholders, building relationships and understanding how different people receive information in different ways, I have been able to successfully introduce new reports wherever I have worked.

Professional Since: 
Mar-2009 (15.1 yrs experience)
Oldest experience: 
Mar 2009 (15.1 yrs experience, WARNING: 0.0 years variance with Professional Since)
Years Experience: 
2

Reporting Specialist, Network Rail, Crossrail & Reading

START Date: 
March, 2009

Current Role - March 2009 – present  : Programme Reporting Specialist (Crossrail Programme and Reading Station Redevelopment)

Reporting Specialist, Network Rail, Crossrail & Reading

START Date: 
March, 2009

Current Role - March 2009 – present  : Programme Reporting Specialist (Crossrail Programme and Reading Station Redevelopment)

Planning & Project Controls Manager, Network Rail, Rail Infrastructure projects

START Date: 
January, 2005
END Date: 
September, 2007

Project controls Manager for a portfolio of Rail Infrastructure Projects

Time and cost analysis using Oracle E business suite and Primavera databases.

Manage the Enterprise planning for the portfolio of projects, cost and time performance of projects, Identifying adverse trends, potential  delays and claims from Contractors. Using Earned Value techniques and ensuring quality data.

Compiling annual business planning, cost and revenue cash flows.

Experience Hours (Planning & Scheduling): 
2800
Experience Hours (Cost Management): 
2400

Planner / Scheduler, Network Rail, NETWORK RAIL

START Date: 
April, 2009
END Date: 
February, 2011

Network Rail, London

Position Held: - Planner / Scheduler

April 2009 – February 2011

Duties Performed:-

  • Preparation of Master Schedule/Interim Milestone for Contractor’s Construction Schedule
  • Review Contractor’s Updated schedule and Integrate to other Projects
  • Track and Manage Baseline Cost and Schedule and Ensure Change Control Process is Implemented
  • Prepare Program Baseline Schedule and Budgeted Cost
  • Re

Junior Scheduler, Network Rail, NETWORK RAIL

START Date: 
July, 2004
END Date: 
February, 2008

Network Rail, London East Side Offices

Position Held: - Junior Scheduler

July 2004 – February 2008

Duties Performed:-

  • Project planning & monitoring using Primavera 3.0
  • Scheduling & rescheduling the activities whenever necessary Co-ordination with Client, Consultants & Sub-Contractors.
  • Projecting weekly & monthly look ahead and taking necessary action to complete the activity as per schedule.
  • Allocat

Planner for Consents, Planning Permissions and Key Output 2, Network Rail, Thameslink Programme

START Date: 
December, 2010
END Date: 
March, 2011

 

Network Rail Thameslink Infrastructure Delivery Programme (Project Planner for Key Output 2)

(Contractor Position)

 

The Thameslink Programme:

Commissioning Planner, Network Rail, FTN / GSM-R Programme

START Date: 
January, 2006
END Date: 
May, 2008

 

Network Rail FTN / GSM-R Programme (Planner to the Commissioning team (6 month rolling Contractor Position)                                                                                  

The FTN /GSM-R Programme:

Transmission Design Planner, Network Rail, FTN /GSM-R Programme

START Date: 
January, 2005
END Date: 
July, 2005

 

Project Planner, Network Rail, Various

START Date: 
September, 2009

Planner for Network Rail in Derby.

Working on various projects on the Midland Mainline and East Midlands areas.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.