Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Planning Manager

Planning Manager, Laing O'Rourke, (various projects)

START Date: 
February, 2004
END Date: 
February, 2006

Planning Manager

Overseeing planning dept of 4 No. planners and 2 No. 3d/ 4d modellers

Projects value €10M - €80M

Tender planning throught to construction plans and claims

Logistic plans

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Planning Manager, Leighton Contractors Philippines, Philip Morris Manufacturing Facility

START Date: 
August, 2001
END Date: 
January, 2005

Site Planning Manager on the Philip Morris Process Plant Construction with 3 Assistant Planners. Late Corporate Planning Manager working on Tender Programmes and Projects Overview.

Experience Hours (Planning & Scheduling): 
6500
Experience Hours (Forensic Analysis): 
1000

Planning Manager, AMEC Foster Wheeler, Petro-Chemical/Oil & Gas

START Date: 
October, 2011
END Date: 
July, 2012

Manage Planning Department

Project Audits

Manage & Communicate Change

Standard Planning Templates

Method Statements

Client Relationship

Weekly / Monthly Reports

Planner Competency

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
100

Planning Manager, Mace Limited, Birmingham New Street Station

START Date: 
August, 2011
Senior Planning Manager for Major Construction. Feasibiliy, Tender and Delivery Stages.

Planning Manager, Mace Limited, Birmingham New Street Station

START Date: 
August, 2011

Senior Planning Manager for Major Construction. Feasibiliy, Tender and Delivery Stages.

Planning Manager, Mace Limited, Birmingham New Street Station

START Date: 
August, 2011
Senior Planning Manager for Major Construction. Feasibiliy, Tender and Delivery Stages.

Planning Manager, ALSTOM, Signalling (Interlocking, ERTMS...), Security (PA, PIS, ISM, TETRA...)

START Date: 
June, 2012
Planning Manager for Projects in the railway sector (signalling and security) in addition of supporting the Global Performance Department in different processes and give support in planning and its tools, coaching and supporting the projects for all ALSTOM TIS Spain portfolio in continuous conection to ALSTOM headquarters. Main duties: - Coordinator of the Planning Managers team. - Support to the department for planning processes, KPIs and certifications (ISO, CMMi L3). - Creation of different templates, KPIs and presentations for reporting and Project Management. - Management o
Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
2000

Planning Manager, ALSTOM, Signalling (Interlocking, ERTMS...), Security (PA, PIS, ISM, TETRA...)

START Date: 
June, 2012

Planning Manager for Projects in the railway sector (signalling and security) in addition of supporting the Global Performance Department in different processes and give support in planning and its tools, coaching and supporting the projects for all ALSTOM TIS Spain portfolio in continuous conection to ALSTOM headquarters.

Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
2000

Planning Manager, Lend Lease, East Village Retrofit Programme

START Date: 
February, 2015

Planning manager to the East Village retrofit accommodation programme to return the Olympic Athletes accommodation back to the public domain.  The site comprises of 2800 accommodation units which are a mixture of market properties, shared ownership and social accommodation units.  Leading a team of 6 planners in the delivery of programme, project control and planning services.  Reporting internally direct to the Head of Programme Delivery and indirectly to the Olympic Delivery Authority. 

Experience Hours (Planning & Scheduling): 
900

Planning Manager, Bovis Lend Lease, Scottish Exhibition & Conference Centre Hydro Arena

START Date: 
April, 2013
END Date: 
August, 2013

Planning consultant to the, 12,000 seated ‘Hydro’ exhibition and concert arena, Glasgow.  Mobilised in the close out stages of the project to provide an accelerated construction and close-out (Primavera) programme.  Introduction of a number of project control tracker tools and overall programme dashboard reports which streamlined the site reporting process and provided Senior Mnanagement and the Client with a realistic prediction of the completion date. 

Experience Hours (Planning & Scheduling): 
800

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content