START Date:
January, 2009
RESPONSIBILITIES AS PROJECT SCHEDULER:
- Plan and schedule construction work and work crew
- Gather and analyze information to prepare reports on the progress of projects
EXPERIENCES GAINED:
- Experience in planning and monitoring of thermal power plant projects
PROJECT HANDLED:
Project Name: Coal-Fired Thermal Power Plant
Client: Electrabel
Duration: March 2009 – February 2011