Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Distance Histogram

1 reply [Last post]
Vignesh S
User offline. Last seen 7 years 9 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

While showing qunatity hisotgram along the distance scale, the graph shows double the times of actual quantity. For example, if my activity qty is 378 cum, the graph shows the cummulative qty as 756 cum. Kindly anyone help me sorting out this issue.

Replies

Antonua Ge
User offline. Last seen 4 years 13 weeks ago. Offline
Joined: 28 Jun 2019
Posts: 8
Groups: None

Well interesting info, so, I think showing qunatity hisotgram along the distance scale is great!!