How can i hide or show the critical distance and time floats in Tilos?

2 replies [Last post]
serkan nari
User offline. Last seen 43 weeks 2 days ago. Offline

when i was working on it i had problem to hide the critical distence and floats

and also to show the critical distance and time floats...

can anyone help me on it?

Best Regards

Serkan

Replies

serkan nari
User offline. Last seen 43 weeks 2 days ago. Offline

Dear Thorsten,

I meant that critical activities on distance diagram. Now I understand that I can display/switch off all CPM terms.

On display tab I found the icons to display Links, Total float, Free float, Constraints, Critical path, Baseline tasks, Progress info, Calendars and more, here there are more items than I need :)

Thank you for your kind help!

Thorsten Balthasar
User offline. Last seen 22 weeks 17 hours ago. Offline

Hi Serkan,

the critical path and the floats are calculated results from the reschedule. The definition is very similar to the CPM float definition. To can switch on/of the display of the float and critical path in the time-distance view: Please select the time-distance cell first, then use the tab "Display" and check the flags "Critical Path", "Total float" or "Free float".

Regarding the critical distance: What do you understand as critical distance?

 

Good Luck

Thorsten

 

TILOS Website: http://www.tilos.org

Market Place

We want to build software that solves real problems, allow people to work more productive and happier.
The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.
The book is designed for users of earlier versions to upgrade their skills and for new planners to learn the software.
A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles.
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects