How can i hide or show the critical distance and time floats in Tilos?
when i was working on it i had problem to hide the critical distence and floats
and also to show the critical distance and time floats...
can anyone help me on it?
Best Regards
Serkan
Dear Thorsten,
I meant that critical activities on distance diagram. Now I understand that I can display/switch off all CPM terms.
On display tab I found the icons to display Links, Total float, Free float, Constraints, Critical path, Baseline tasks, Progress info, Calendars and more, here there are more items than I need :)
Thank you for your kind help!
Hi Serkan,
the critical path and the floats are calculated results from the reschedule. The definition is very similar to the CPM float definition. To can switch on/of the display of the float and critical path in the time-distance view: Please select the time-distance cell first, then use the tab "Display" and check the flags "Critical Path", "Total float" or "Free float".
Regarding the critical distance: What do you understand as critical distance?
Good Luck
Thorsten
TILOS Website: http://www.tilos.org