Link lines in Time Distance View

2 replies [Last post]
Vignesh S
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

In the project which I am working on, most of the activities have more than one predecessor/successor links(usually 5+). Also, no. of activities is 1000+. If I link all of them, the time-distance view looks much clumsy and there is no clarity of schedule presentation. But, none of the links are avoidable as it will affect the dpendency logic behind the schedule and future updation of the schedule will also be a cumbersome one. Is there any option available to make some of the link lines invisible.???

Replies

Vignesh S
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

Alexandre,

Thanks for the nice suggestion and this works well as per my requirement.

Vignesh