Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Weight Factor

6 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi All,

i have a project has five WBS and each one of them has a duration and cost, and i need to determine weigth factor for each wbs based on time and cost, is there any method to do that, or there is another method to determine the weight factor?

best,

muataz

Replies

Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline

ِDear Testro

Hi,

you are right, but my method is a simple sample for buttom up approach. the best solution depend on Create S.W.U for Project.

 

B/R

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Cost is not a reliable method of reporting progress.

Your split of 70 / 30 is too broad an average when in some task the split is 20 / 80 and others 90 / 10.

If you are going to apply this method then you must allocate the correct split to each task.

Also there is a 3rd split of OH&P which is not progress related at all.

Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline

Dear moutaz

Hi,

the best way for create weight factors as following items:

1- Cost ( 70 % share)

2- Time ( 30 % share)

Total weight= 70% w.cost+ 30% w.Time

Also you need determain the S.W.U ( Specific Work Units) for in the WBS units.

 

Best Regards

Rashidi

moutaz aldeib
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Jithin

the case i have is not construction and both time and cost are preferable to be used, my question is how to use both?

best,

muataz

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Moutaz

Weightage only becomes a problem when a planned task s a combination of trades and/or location ie:

FRC Suspended slabs : 20-10-17 > 15-12-17 > 40d

When this task is spread over - say - 5 slabs then you have both a time and cost weithage problem.

This is because planners are lazy and lack pride in their profession.

It is just as easy to plan the work in detail ie:

Level 1

Slab Form > Rebar > Edge Forms > Pour Concrete

Level 2

                Slab Form > Rebar > Edge Forms > Pour Concrete

Etc

Then you just report % complete in either time or volume on each task.

Best regards

Mike T.

Jithin Kambhikanam
User offline. Last seen 2 weeks 2 days ago. Offline

Hi Moutaz,

To Calulate weightage you can do it by either

  • By Only Cost
  • By Time and Cost

If the Project is only Construction then Manhours / Activity would be good.

If the Project is Engineering, Procurement and Construction then it would be better to use Manhours / Deliverable, Cost / Item and Manhours / Activity to measure each WBS.

 

In an Overall summary ou can use Cost or the weightage given by Client.

 

Regards

Jithin