Total Manpower

2 replies [Last post]
ronron martinez
User offline. Last seen 48 weeks 6 days ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear All,

, I got a project that will complete within 2-1/2 yrs with estimted manhour of 175,000 Hours, I drafted a schedule that loaded with manpower. Expert advise how much direct workers required to complete the work activity. Thanks a lot.

Regards

Ron

Replies

As was discussed before resource hours and resource quantities are not proportional.

But in any case the number of workers is not the same during the project life cycle. The number of workers at any time is determined by the project schedule.

Zoltan Palffy
User offline. Last seen 3 days 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1588

if you have the estimated manhours then you should know out of the 175,000 manhours how much is direct and indirect how did you come uo with this numebr in the first place ?