Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost Budgeting vs. Cost Estimating

4 replies [Last post]
Carmen Muñoz
User offline. Last seen 18 years 27 weeks ago. Offline
Joined: 23 Oct 2005
Posts: 4
Hi, could anyone tell me what’s the difference between Cost Budgeting and Cost Estimating, please? Thank you.

Replies

manulal inasu
User offline. Last seen 18 years 15 weeks ago. Offline
Joined: 15 Oct 2005
Posts: 52
Groups: None
Hi Carmen

An important aspect of controlling costs on a Job or project is to know not only the costs already booked to a job, but also those costs to which you are already committed through purchase orders you have placed with suppliers. These job commitments become costs as purchase orders are delivered and suppliers submit invoices for payment.

Earned value is simply the budgeted cost of whatever work you have completed.

Committed cost comes under actual cost calculation.

Regards,

Manu
Naveed Tariq, PE,...
User offline. Last seen 14 years 49 weeks ago. Offline
Joined: 19 Dec 2002
Posts: 45
Groups: None
An estimate is a best guess/projection of the eventual cost.

Budget is the distribution of estimate over time. (Monthly cash flows)

You can use this definition for both resource and cost.

Cheers!!
Carmen Muñoz
User offline. Last seen 18 years 27 weeks ago. Offline
Joined: 23 Oct 2005
Posts: 4
Thank you for your response. Although I know this forum specializes in planning and scheduling, I am pretty sure there are professionals with experience in the cost control area. I would appreciate any brief idea of what cost commitment is. I also would like to know if the use of cost commitment excludes the use of earned value (and viceversa). Thank you again.
Bernard Ertl
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
An estimate is a best guess/projection of the eventual cost.

A budget is the amount of money available/approved to get the job done.

The budget is usually based upon an estimate, but may be higher or lower.

Bernard Ertl
InterPlan Systems