Hey Guys & Gals,
Need to pick your brains on a little issue......
I have compiled an integrated schedule of 5 projects in (Optional Client 8.1) clearly showing their interdependencies and Key Interface Milestones so select data can be reported to the board.
Due to the typical (non) availability of each PM, although each project has the same Data Date, in the first instance I copied the Schedule ( and then on this copy I deleted the other projects I didnt need) so I could update & keep the original data intact as I rescheduled to a more current date.
Still with me.....? Good :-)
Now, when I copy this 'standalone' project back into the WBS of the integrated schedule, the calendars are automatically changed to the global default calendar. This changes all the 7 day calendars in my schedule back to the default 5 Day.
Each project should be scheduled on its own Data Date (as clearly stated when scheduling multiple projects simultaneously), but for some reason it isnt maintaining the correct calendars and all my weekend activities are pushed out to the Monday etc.
Does anyone know why it does this? And more imprtant, how to fully maintain each Activites correct calendar?
Scheduling the entire programme just for one specific element isn't aviable option as it would take far too long to update the remaining projects as a result - they will have all been scheduled to the current Data Date but with no update!
I also have 8.3, haven't tried importing as yet but I'm guessing it's no different.
Any help muchos gracias
Walshy