Wronge start / finish date

3 replies [Last post]
Samer Hozin
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 25 Dec 2010
Posts: 2
Groups: None

I set the project calender to 12 Hrs/ Day 7 Day/weeks and also the admin user pereference to 12 Hrs / day and check all user to specify the number of hous for each time period .

my problem is when I try to make - 6 hours lag for an activity it give me wronge start date for it

for example the activty by default start at 21 spep. 2PM and after assign -6 Hrs alg it start at 19 sep 10 AM ?

Replies

Raymund de Laza
User offline. Last seen 28 weeks 20 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Set the New Created calendar as your default calendar.

Samer Hozin
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 25 Dec 2010
Posts: 2
Groups: None

Sir

thank you for the replay

I assign lag because i want to start the successor activty late by 6 hrs before other activity finsh and sure it FS also the project calender is 12 hrs / day 7days / week and not link to globe calender , so why this happens

Mike Testro
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Samer

Welcome to Planning Planet.

Why are you applying peculiar lags anyway?

The correct linkage should be Finish Start between all tasks and that will solve your problems.

21st September 2012 is a Friday so maybe you are linking back across an Islamic weekend.

Best regards

Mike Testro