P6 start & finishes fixed

6 replies [Last post]
Bill OBrien
User offline. Last seen 1 year 6 days ago. Offline
Joined: 19 Feb 2007
Posts: 13
Groups: None

I am creating a revised target program. I have a number of activities which start dates are pushing out past the data date or will not fix to the date I assign. These activities have no constraints and no relationships! Something is driving them but it is unclear what. The start and finish dates show a star symbol even though no constraints or relationships are assigned? Has anyone come across this before?

Replies

Anning Sofi
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

There are other ways to clear the external links, but Frederick method is quick and simple.

Bill OBrien
User offline. Last seen 1 year 6 days ago. Offline
Joined: 19 Feb 2007
Posts: 13
Groups: None

Just checked my External links and your correct.

Frederic your a legend, thank you very much.

Its always somthing simple....

Aldrin Morallos
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 1 Jun 2011
Posts: 5
Groups: None

Bill,

 

Try to open up the Predecessor or Relationship Column.

Frederic Fasquelle
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Bill,

I faced the same issue: Star symbol on finish dates while no constraint was assigned.
It was coming from field "External finish date". Indeed, when some inter-project relationship are lost, P6 is constraining Early/late dates. Like this, it is artificially keeping time logic.

To recover a proper schedule, add column "External finish date" and manually remove date within cells.
Launch calculation, everything should be OK,

regards

Kannan CP
User offline. Last seen 1 year 15 weeks ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Bill,

Check the Planned Start dta and the Data Date.

Kannan

Bill OBrien
User offline. Last seen 1 year 6 days ago. Offline
Joined: 19 Feb 2007
Posts: 13