Total Float Bar on Completed Activities

2 replies [Last post]
Utku Çil
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 7 Jun 2011
Posts: 29

Is there a way that I can remove the total float bar on completed activites?

I have an on-going schedule having completed, in progress & not started activities as can be predicted but I want to see the total float bar only for in progress & not started activities since, in my opinion, total float does not mean anything for completed activites.

Thanks in advance for who replies..

Replies

Utku Çil
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 7 Jun 2011
Posts: 29

Thank you Gary,

It seems to be really simple as I guessed :)

Gary Whitehead
User offline. Last seen 4 years 45 weeks ago. Offline

See extract from a Paul Harris presentation covering this:

 