Is there a way that I can remove the total float bar on completed activites?
I have an on-going schedule having completed, in progress & not started activities as can be predicted but I want to see the total float bar only for in progress & not started activities since, in my opinion, total float does not mean anything for completed activites.
Thanks in advance for who replies..