Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Earned Value - At Completion values with Current dates

2 replies [Last post]
Haresh Jayanth
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

In Admin Preferences , Earned value tab , we have 3 methods to choose earned value

1) Budget value with Planned dates.

2) Budget values with Current dates.

3) At completion value with current dates.

I have a clear idea the use of the first two. But i want somebody to explain what is use of having " At completion values with current dates to compute Earned value management.

Pls help.

 

regards,

 

Haresh Jayanth - PMP

Replies

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2433
Groups: None

the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.

Dinesh Kumar
User offline. Last seen 1 week 6 days ago. Offline
Joined: 8 May 2006
Posts: 29

1) Budgeted value with planned dates

PV = budget value x time spread or budget value x cost spread

 2) Budgeted value with current dates

PV = budget x current elapsed duration / total duration with expected completion

3) At completion value with current dates

PV = EAC x current elapsed dur / total dur with expected completion