Multi-Resources in Report

1 reply [Last post]
Vaughn Edwards
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 1 May 2008
Posts: 16

If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not all the resource hours show up. Looks like those avtivities that have multi resources assigned to them don't add up in the second report. Any suggestions?????

Replies

Rashid Iqbal
User offline. Last seen 51 weeks 1 day ago. Offline
Joined: 7 Apr 2010
Posts: 67

I ussally export all the data i.e. Resource by Act ID and then use the Pivot tabel to prepare the report. Just trying doing all the sort, filtering in Excel. Thanks.