Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Multi-Resources in Report

1 reply [Last post]
Vaughn Edwards
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 1 May 2008
Posts: 16

If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not all the resource hours show up. Looks like those avtivities that have multi resources assigned to them don't add up in the second report. Any suggestions?????

Replies

Rashid Iqbal
User offline. Last seen 3 years 13 weeks ago. Offline
Joined: 7 Apr 2010
Posts: 70

I ussally export all the data i.e. Resource by Act ID and then use the Pivot tabel to prepare the report. Just trying doing all the sort, filtering in Excel. Thanks.