Updating sequence via excel spreadsheet

1 reply [Last post]
Izam Zakaria
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

If in P3, we can import/export the links thru excel, can we do that in P6?I never give a try yet but if not mistaken we can do exactly same like P3. Am i right?

Regards
I-zam

Replies

Rodel Marasigan
User offline. Last seen 2 weeks 15 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
Yes you can use export/import spreadsheet function in P6 to update progress. Task is for updating activities and Resource assignment is for updating resource loading and actual. You must update one at a time and not both otherwise it will produce an unexpected result.