Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Spreadsheet Fields in Activity Usage Spreadsheet

2 replies [Last post]
Mohd Syahrul
User offline. Last seen 12 years 5 weeks ago. Offline
Joined: 9 Nov 2010
Posts: 13
Guys, could someone point me how to select "cum remainimg early unit" which same as in Resource Usage Spreadsheet. Thanks There is no 'custumize' spreadsheet options in Actity Usage.

Replies

Mohd Syahrul
User offline. Last seen 12 years 5 weeks ago. Offline
Joined: 9 Nov 2010
Posts: 13

Thanks Amit but that seems my problem since I cannot find the "customize" option in activity usage speadsheets's column. Hope that you can point me step by step.

Amit Parmar (PMP)
User offline. Last seen 11 years 31 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

Right click on the column in you activity usage spreadsheet...and choose customise...you will be able to choose the desire column that you want.

Regards

Amit