activity name

3 replies [Last post]
Rola Sabbah
User offline. Last seen 10 years 26 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
hi
how can we replace a word in ths activity name with another?
like floor no.
of course using global change

Replies

Rodel Marasigan
User offline. Last seen 2 days 5 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Rola,
Global change is not possible if your data are coming from different rows of a table. That is for Replace functions which is Ctrl+r or Edit-> Replace
Another way is to Export to Excel, modify Activity Name then import back.
Rola Sabbah
User offline. Last seen 10 years 26 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
rodel
lets say we have a building consisting of 35 floors, we inserted activities for the first floor, such as : excavation for first floor.
now you want to copy the activities to the other floors but with out ’first floor:.
i tried substring functions but it didn’t work, you want me to add a UDF and then what? shal i insert floor No in that column? ok but the problem is with Replace function if it exists in p6!!!!!
Any ideas?
Rodel Marasigan
User offline. Last seen 2 days 5 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Rola,
What is your basis for Global change? It can be done but it requires fields where it coming from (i.e. UDF)