Joined: 24 Aug 2006
Posts: 219
Dear Rodel,

I have 8500 activities in my program. When i do scheduling i.e. F9 , it is taking time more than one minute. Is there any way i can shorten the scheduling time for program by changing any settings.

regards,

Haresh

Replies

Rodel Marasigan
User offline. Last seen 1 day 44 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
Change the Start up filter.
Edit-> Users Preferences-> Start up filter. Change to open project only. If still taking time you need more ram.