Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Linking more than one project at same time

No replies
Zeinab El-Beialy
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 24 Mar 2008
Posts: 11
Groups: None
dear all?

kindly help me in this matter please, for the purpose of monitoring one of the detailed project timeschedules that including the resources and activity codes, I want to link it to another one only including WBS showing the main departments like arch, elec, mech, ....
so I want to show through it the actual and planned budgeted units, and actual start and finish

and to be filtered by departments and the other time to be filtered by stage.

I am using P6.2


Thanks for help,
Zeinab