How to Make PDF from more than one layouts in one go

No replies
Mohammad Rahmani
User offline. Last seen 2 years 11 weeks ago. Offline
Joined: 18 Jan 2016
Posts: 3
Groups: None

Hi All

Good morning, 

 

I have below question and I appreciate if you give me any soultion,

 

I have 8 projects and more than 40 contractors and one layout for each, every week I create 40 layouts and 40 repetitive works, is there any way to create PDfs from layouts in one click?

 

I also tried reports but as I have more than one projects open it dosen't save my repoort, and I think it is a bug from Oracle.

 

I look forward for any suggestion and thanks from now.

Stay safe

Mohammad

Zoltan Palffy
User offline. Last seen 16 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

in P6 go to tools then reports then batch reports and batch them