Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adding Same Resource more than once

8 replies [Last post]
Planning guy
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 28 Jun 2011
Posts: 7
Groups: None

Hi

how are you guys.

I am facing one problem.

I want to assign same resource more than once in one activity.

e.g there are 20 Labors in one activity ( 100 dollar / day/ labor) . how to assign this 20 Labor to single activity.

Kindly help.

Planning_guy

Replies

Planning guy
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 28 Jun 2011
Posts: 7
Groups: None

ya i am new thanks for sharing.........

AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

I think you are new in primavera.Follow this

No Adding process is different it is added in Remaining units/time

in this case..20*No of Hrz pr day and Write it in REmaining unit pr time

eg

20 Labors are working at 8 Hrz a day the 20*8=160

write 160 in Remaining hrz/day..Budgeted will be calculated auromatically

 

I think its clear now?

Planning guy
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 28 Jun 2011
Posts: 7
Groups: None

Ya i know this is planned units , but where to input it in "Budgeted units"... in resource tabs...?

AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

No Thesee are Planned.Actual will be added after the activity Starts.

Planning guy
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 28 Jun 2011
Posts: 7
Groups: None

Will it be the "Actual units" = 100 ...?/

AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

First Add Resource in Resource window

Return to Activity Window and click on activity to which u want to assign resource.

Click on Resource Tab... and Assign..then right the unit (in your case 20*5=100)

Planning guy
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 28 Jun 2011
Posts: 7
Groups: None

how to input it in P6.??

AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

20 * No.of  days

 

For example,you have an activity where 20 labors will work for 5 days

20*5=100