Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updated Schedule as Baseline

5 replies [Last post]
Dinesh Kumar Dama...
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Dear experts,

I am exploring an option of approving an updated schedule as the baseline schedule. I would like get feedback from the experts on possible issues and problems with that or any thing you want to share with us on this.

I’d appreciate your feedback on this.

Thanks & regards

Dinesh Kumar

Replies

Rodel Marasigan
User offline. Last seen 20 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Dinesh,
I always used updated data as a baseline for calculating EV, comparison, cost analysis, what if... etc and no problem at all. As long as you know what you are doing and like what I have said, P6 use planned date and not actual date when use in baseline. If the updated data is used and planned date as still intact but if you need the actual date and value to used then you need to modify planned date to match with actual date. Below link is might be helpful to you.
How to set Baseline- After revised the Schedule and to Post#2
Dinesh Kumar Dama...
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Rodel

Thank you for your reply. I am not worried about the contractual part rather I am worried about P6 capabilities in terms calculating earned value, planned value, displaying baseline dates etc. Have you experienced any such issues or problems when you assigned the updated schedule as the baseline?

Thansk & regards

Dinesh
Rodel Marasigan
User offline. Last seen 20 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Dinesh,
Approving baseline that effect the critical path or having contractual issue like extending duration of completion is like giving them an EOT. You must be very careful because EOT might have cost associated with it. All document submitted associated to re-baseline must carefully review if their entitlement of EOT is valid or re-baseline is required.

Note: Using updated schedule as baseline is not an issue as long as there is no effect on critical path or any contractual issue or obligation. Aside from that P6 use planned date for baseline and not actual dates unless updated schedule is modified to reflect actual date = planned date.

If you are on contactor side then all documents to prove that re-baseline is required must be prepared by you or your planner to substantiate the re-baseline so the client will buy it.

Best Regards,
Rodel
Dinesh Kumar Dama...
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Rodel

I am on the client side. Actually it does not matter whether you are on the client side or the contractor side. I am just trying to understand of any issues arising out of using updated schedule as baseline.

Thanks ^regards

Dinesh
Rodel Marasigan
User offline. Last seen 20 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Dinesh,
I’m not sure if I get the message correctly. Are you on the client side or contractor side? Is there any contractual issue affected?