Budget Units is linked to Duration

2 replies [Last post]
Haresh Jayanth
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Dear Rodel,

I have one problem, whenever i change my Budgeted units of any resources then my duration changes.......The activity type is task dependant......Can you guide me.....why resource budgeted units is linked to duration......

regards,

Haresh

Replies

Rodel Marasigan
User offline. Last seen 20 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
The reason why your duration change when budget units is change because you use a duration type "Fixed Units" or "Fixed Unit/Time" and resource "Drive Activity Date" is tick. If you used this duration type settings and don’t want to affect your duration when changing Budget Units then you have to un-tick "Drive Activity Date" under resource assignment on each resource. Alternatively use Fixed Duration and Unit" or "Fixed Duration and Unit/Time". Using this settings will ignore "Drive Activity Date" settings on resource which I already explain to your before when you are querying about P3.x Driving resource equivalent to P6.
PINAN T.
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
Try to Use Duration type Fixed Duration and Units