Commencement Date

3 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Planners,

I am reviewing a baseline schedule, the commencement date has TF=2 days?

Regards,

Moutaz

Replies

Roger Booth
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 74
Groups: None
Check your calendar. If the calendar is a 5 day week and the commencement date is at a weekend, it will show float equal to the duration until you start work on the Monday
moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Ali,

The problem is that the commencement date should have TF=0 and linked to the critical activities which have TF=0, also in the schedule report I have found "Milestone with invalid relationship"

Regards
Ali Farhat
User offline. Last seen 14 years 50 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
so where is the problem?