Primavera automaticaly inputting budegeted labour unit?

13 replies [Last post]
John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
Hi all,
I have found a problem in my primavera program. I didnt assign any labour type resources to the activities of my program. But in Budget Labour units column, Primavera is showing some values?
Why it is coming like this?
How we can fix this problem?
Can any one help me.......
Thanks in advance.......

Replies

Zoltan Palffy
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

recourses can not automatically assign themselves to activities so someone had to do this 

Syam Mohan
User offline. Last seen 7 years 12 weeks ago. Offline
Joined: 26 Mar 2016
Posts: 5
Groups: None

hello everyone,

                      I want to create generate histogram for office staff and direct labour. How it is possible.?

 

Godstime Mega
User offline. Last seen 9 years 37 weeks ago. Offline
Joined: 7 Jul 2014
Posts: 4
Groups: GPC Qatar

hello everyone here , please i wanted to know more about  (REMAINING UNIT/TIME and AT COMPLETE UNIT) the reason i wanna know is that if  I assign 1 to my  REMAINING  UNIT/TIME , MY AT COMPLETE will automatically change to 42 , when its  remaining unit is 2 my at complete will automatically change to 84..... please  can anyone help on how to go about the calculations

thanks

John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
Thank you Mr. Rodel for your reply...\
I am using Primavera 6.0...
Rodel Marasigan
User offline. Last seen 6 weeks 17 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Sorry John,
The old Knowledgebase site is gone and redirecting to Oracle site. I logon and tried to find but nothing found.
There must be some patch like SP1 & SP2 but I’m not sure. What version of P6 are you using? I have 6.1 & 6.2 and both of them don’t have problem.
John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
Yor are correct Mr. Rodel
But i find in internet that this type of error is occuring in P6 commonly.
I am pasting that link here
http://forums.oracle.com/forums/thread.jspa?messageID=3378954
in this link it is mentioned that
Please
reference Solution ID
prim18501 in
our Knowledgebase for anothere cause and more
information on "No resources assigned but Budgeted
Planned Labor units does not equal zero (0)"

but i couldn’t access to this knowledgedata base?
can you please check with this
Rodel Marasigan
User offline. Last seen 6 weeks 17 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
John,
If the Project was inherit or import from others you don’t have any control on what’s on the file until you manage to fix it. If the Project was newly created by you then you are aware of the history whether you did something or not.
John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
Thank you Mr. Rodel..
but i find the same problem with other project plan also..
what may be possible reason for that?
Rodel Marasigan
User offline. Last seen 6 weeks 17 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
John,
That’s the reason why. He might do something that you are not aware of.
John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
I am not the one who create this program.
Actually i import it from other person...
Rodel Marasigan
User offline. Last seen 6 weeks 17 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
John,
Did you create the Project or inherit/ import from someone?
John Paul Augustine
User offline. Last seen 15 years 19 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 19
No i didn’t input any cost in the Activity Detail-> Status tab-> Labor Cost -> Budget field..

I already corrected by filling down the budgetted labour units to zero manually..
But i should like to know why it is coming like this?
is there any settings i need to change in Primavera????/
Rodel Marasigan
User offline. Last seen 6 weeks 17 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi John,
Did you put any cost on the Activity Detail-> Status tab-> Labor Cost -> Budget field?